Submittal review comments and resubmittals

How to respond to reviewer comments on a returned construction submittal and prepare a clean resubmittal that gets approved.

Reading the review stamp

Reviewers return submittals as approved, approved as noted, revise and resubmit, or rejected. Revise and resubmit means at least one requirement is not yet shown to comply; the comments say which.

Answering each comment

Number each reviewer comment, tie it to the specification paragraph it touches, and write a short response that states what the package now shows. If the requirement is still open, say what is outstanding instead of claiming it is met.

Preparing the resubmittal

Revise only what the comments require, mark the revision, and include the response list so the reviewer can confirm each item quickly. SUBNEXUS imports the reviewer's comments, matches them to requirements, and drafts responses from the actual requirement status for you to edit.

Why it saves time

Clear, traceable responses shorten review cycles, and fewer cycles keep procurement and installation on schedule.

Quick answers

How long does a resubmittal take?

The spec sets the review period, often ten to fourteen days per cycle. Clean responses reduce the number of cycles.

What does approved as noted mean?

The item is approved with the reviewer's notes applied; the contractor must follow the notes.